Assume every service is live until it's located, isolated and tested. No intrusive work starts on a maybe.

Field guideOwner · Site SupervisorRPD WHS Manual V8.0
Start safeControl the riskStop when it changes
Scroll the journey
1

When it applies

If you're doing any of this, this guide is in play.

Electrical
Hydraulic
Gas
Communications
Fire
Water
Stormwater
Embedded services
2

Before you start

Before the work begins, the Site Supervisor confirms — and you check your own work area.

Drawings

Scan where required

Isolation points

Lock-out / tag-out

Affected duty holders

3

The controls

Work down the hierarchy — collective protection first, PPE last. PPE never carries the job on its own.

EliminateDesign the hazard out
SubstituteUse a lower-risk method
IsolateSeparate people from the hazard
EngineeringGuard, extract, contain
AdminSWMS, permits, training, signage
PPELast line — fitted & worn

The RPD rule

Use permits and isolation for intrusive work. Lock, tag and test before work. Keep an exclusion zone around live services.

PermitLocateLOTOTest before touchExclusion zone
Hold point — never skip

No intrusive work starts until services are located and isolation status is verified.

Locate, isolate, lock, tag and test. A service you can't prove is dead is treated as live.

5

Stop & escalate

See any one of these? The job stops until it's fixed — no exceptions.

  • An unidentified service is found
  • Isolation cannot be confirmed
Stop work→ tell the Site Supervisor → don't restart until the control is back and the SWMS is reviewed.
6

What gets recorded

The job isn't done until the evidence exists. Live records go in Breadcrumb.

Breadcrumb · live site

  • Permits
  • SWMS
  • Pre-starts & toolbox talks
  • Site alerts for isolation / exclusion zones
  • Hazard reporting for unidentified services